Connect with us

Power

Electricity subsidy dips to N514.35b in Q2 2025

Published

on

• DisCos collect ₦564.71 billion revenue; International customers pay $9.01m

The Nigerian Electricity Regulatory Commission (NERC) has said the cost of Federal Government electricity subsidy reduced to N514.35 billion in the second quarter of 2025 (Q2 2025) from the N536.40 paid in the Q1 2025. The decline was by 4.11 per cent, according to the commission’s Q3 Report.
The payment of subsidy, the report noted, was incurred due to lack of a cost-reflective tariff.
NERC said, “The total amount invoiced by the GenCos for energy delivered to each DisCo and the DRO- adjusted NBET invoice to the respective DisCos during 2025/Q2.
“It is important to note that due to the absence of cost-reflective tariffs across all DisCos, the Government incurred a subsidy obligation of ₦514.35 billion 21; this represents a ₦22.04 billion (-4.11 per cent) reduction in FGN subsidy compared to 2025/Q1 (₦536.40 billion).”
The report also noted that although the subsidy obligation of the government decreased in naira terms (-₦22.04 billion), it accounted for 59.60 per cent of the total GenCo invoice, which is a
0.44pp increase compared to 2025/Q1 when subsidy accounted for 59.16 per cent of the total GenCo invoice.
NERC said this is because the actual generation cost (₦/kWh) increased by 0.59 per cent, while the allowed end-user tariffs remained unchanged across the quarters.
According to the report, the total revenue collected by all DisCos in 2025/Q2 was ₦564.71 billion out of the ₦742.34 billion that was billed to customers.
This, said NERC, translates to a collection efficiency of 76.07 per cent.
In comparison, the report said, the total revenue collected by all DisCos in 2025/Q1 was ₦553.63 billion out of the ₦744.26 billion billed to customers, which translated to a 74.39 per cent collection efficiency.
This means that at an aggregate level, DisCos recorded a 1.68pp increase in collection efficiency between 2025/Q1 and 2025/Q2, according to the report.
NERC revealed that in 2025/Q2, three DisCos recorded collection efficiencies greater than 80 per cent with Eko (87.80 per cent) recording the highest collection efficiency.
Conversely, it said Jos DisCo recorded the lowest collection efficiency at 43.82 per cent .
It added that on there other hand, the remaining five DisCos recorded declines in collection efficiency, with Abuja (-3.93pp) and Jos (-3.37pp) DisCos having the most significant declines
across the quarters.
NERC explained that the Market Operator issues invoices to DisCos for energy transmission and administrative services.
The report said the period under review, DisCos made a total remittance of ₦65.30 billion against the cumulative invoice of ₦68.68 billion issued by the MO.
This payment, according to the report, translates to 95.07 per cent remittance performance and is a 1.25pp decrease
when compared to 96.32 per cent remittance performance recorded in 2025/Q1 when DisCos remitted ₦59.49 billion out of ₦61.76 billion invoice issued by the MO.
On the remittances made by bilateral customers (domestic and international) and special customers for invoices issued in 2025/Q2 by the MO, NERC noted they are the six international bilateral customers being supplied by GenCos in the NESI made a payment of $9.01 million against the cumulative invoice of $17.54 million issued by the MO for services rendered in 2025/Q2, translating to a remittance performance of 51.33 per cent .
It also said the domestic bilateral customers made a cumulative payment of ₦1.401.00 billion against the invoice of ₦2.796.29 billion issued to them by the MO for services rendered in 2025/Q2, translating to 50.10 per cent remittance performance.
The report explained that one domestic bilateral customer made payments during 2025/Q2 for outstanding MO invoices from previous quarters.
NERC said the MO received ₦10.53 million from Trans-Amadi (OAU/FMPI) towards outstanding invoices from previous quarters.
Meanwhile, it said the special customer (Ajaokuta Steel Co. Ltd and the host community) did not make any payment towards the ₦1.27 billion (NBET) and ₦0.12 billion (MO) invoices received in 2025/Q2.
It explained that this continues a longstanding trend of non-payment by this customer, and the Commission has communicated the need for intervention on this issue to the relevant FGN authorities.

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Power

NERC cuts regional transmission loss target from 7.24% to 7%

Published

on

Determined to continually improve transparency and efficiency in the country’s power grid through enhanced reporting of Regional Transmission Loss Factors (TLF), the Nigerian Electricity Regulatory Commission (NERC) has issued Order No. NERC/2026/026, which reduces the regional TLC operated by the Transmission Company of Nigeria (TCN) from 7.24 per cent in 2025 to align with the seven per cent benchmark under the Multi-Year Tariff Order (MYTO), with a further target of lowering it further to 6.5 per cent by December 2026.

 

The directive was contained in a public notice accompanying the Commission’s Order on reporting regional electricity transmission loss factors dated April 9, 2026.

 

Data from the Nigerian Independent System Operator (NISO) showed the national average TLF declined from 8.71 per cent in 2024 to 7.24 per cent in 2025, which still remains above the seven per cent multi year tariff order (MYTO) benchmark, prompting the establishment of a formal reporting framework effective yesterday under the Electricity Act 2023.

 

The Commission also issued directives for NISO to install smart meters at regional boundaries, measure and document transformer energy flows and file quarterly reports. The TCN is also expected to submit a loss-reduction action plan later in July and ensure compliance with a 6.5 per cent cap by year-end.

“NISO to file quarterly reports on TLF to NERC on a regional basis TCN to ensure that TLF across transmission regions shall not exceed 6.5% by December 2026,” NERC said in the statement.

Continue Reading

Power

President Tinubu approves N3.3 trillion final settlement on legacy power sector debt

Published

on

• 15 power plants signs settling agreements totalling ₦2.3 trillion.

• Gencos: “We agreed N4 trillion debt owed as at December 2024

• CPPE: “President deserves commendation for paying legacy debt”

A boost for power stability in the country emerged yesterday as President Bola Tinubu yesterday approved the payment of N3.3 trillion as final settlement for legacy debts owed the power sector. The President also approved the payment plan to settle the outstanding debts under the Presidential Power Sector Financial Reforms Programme.

The debt repayment plan followed the final review of the legacy debts that have beset the power sector for more than a decade. The long-standing debts accumulated between February 2015 and March 2025.
In a statement signed by the Special Adviser to the President on Information and Strategy, Bayo Onanuga, the approval follows the verification of the claims.

“₦3.3 trillion has been agreed as a full and final settlement, ensuring a fair and transparent resolution. Implementation has begun, with 15 power plants signing settlement agreements totalling ₦2.3 trillion. The Federal Government has already raised ₦501 billion to fund these payments. Out of the amount, N223 billion has been disbursed, with further payments underway,” the statement read.
Stakeholders maintained that with payments reaching the power value chain, generation will be more stable, and with power plants supported, electricity reliability will improve , and as the sector stabilises, more investment, more jobs, and better service will follow.

“This programme is not just about settling legacy debts. It is about restoring confidence across the power sector — ensuring gas suppliers are paid, power plants can keep running, and the system begins to work more reliably,” explained Olu Arowolo-Verheijen, Special Adviser on Energy to President Tinubu.

“It is part of a broader set of reforms already underway — including better metering and service-based tariffs that link what you pay to the quality of electricity you receive.
“The government is also prioritising power supply to businesses, industries, and small enterprises — because reliable electricity is critical to creating jobs, supporting livelihoods, and growing the economy.
“The goal is simple: more reliable power for homes, stronger support for businesses, and a system that works better for all Nigerians,” she added.
President Tinubu has commended all stakeholders who supported efforts to resolve the legacy issues in the power sector. He has also confirmed that the next phase (Series II) will begin this quarter.

But the Generation Companies (GENCOs), the main arm of the electricity value chain at the centre of the legacy debt, is shocked at how the final amount of N3.3 trillion was arrived at. For the APGC, there are more questions to be answered. For instance, the body insists that it is in the dark over how the final reconciliation conducted to arrive at N3.3 trillion.

The Managing/Chief Executive Officer, Association of Power Generation Companies (APGC), Dr. Joy Ogaji, argued that as at March 2025, the Generation Companies (GENCOs), Ministry of Finance, APGC, and the Nigerian Bulk Electricity Trading (NBET) company, jointly reconciled all the debt of GENCOs and agreed on N4 trillion as debt owed the sector from 2015 to December, 2024.

“The N4 trillion was what they agreed as of March 2025. That was the last reconciliation. All parties signed off that the debt up till December 2024 is N4trillion and it was the basis for which we had a meeting with the President in July in the State House, where he approved the N4 trillion in the form of cash and bond and asked the Minister of Finance and Debt Management Office (DMO) to go and work with the GENCOs to make sure that the legacy debt, and the legacy debt is 2015 to December 2024, that is legacy debt. So, it is not clear at all.

“And then, another part of the statement said that about 15 generation companies have signed off. I want to tell you that it is five GENCOS that have signed off. The companies that I know that have signed off are NDPHC, FIPL, Mabon, and Geregu. There are only five GENCOS that have signed,” Ogaji said.

For now, the APGC helmsman said: “So, I cannot tell you whether we accept the final settlement of N3.3 trillion or not when we don’t know when they did this reconciliation because it is just she, herself, and herself that are doing the reconciliation. The last reconciliation the GENCOs took part was March 2025. And since that time, we have been asking for new reconciliation so that we can know the current debt because the whole of 2025 has ended. As of March, when they reconciled, we have not even concluded the February invoice for 2025. So, we need to start from 2025 January till date. We need to reconcile that one so that we know how much that is.

“All we are asking for is which reconciliation that brought it down from N4 trillion to N3.3 trillion. When did it take place? And when did all the GENCOs sign off on it that now they will accept N3.3trillion? This N3.3trillion is it in bond, or is it in cash? And when will they pay the GENCOs?” Dr. Ogaji asked rhetorically.

But the Chief Executive Officer, Center for the Promotion of Private Enterprise (CPPE), Dr. Muda Yusuf, heaped praises on the federal government for what he described as “bold step” taken to clear the debts despite the challenging of funding it is facing.
“I think we must commend the President for taking such a bold step, despite all the challenges of funding that the government is dealing with. For a government to give priority to this, it shows that the President and the government itself appreciate how critical this power sector challenge is. So for me it’s a very good development and it shows that the government is responsive to the cries of the citizens that this power sector thing has to be fixed.

On the disputed amount, Yusuf said: “whether the amount is N6 trillion or N3 trillion, we all know what it is when it comes to managing subsidies, because it’s a subsidy, more or less, that the government is making available to sustain the provision of electricity. And historically when we deal with subsidy issues, there are always issues about transparency, about equality of claims and all of that. But N3.3 trillion is a major step forward; it is not small money. I think it’s a major step forward and I think that the stakeholders in the sector should embrace this and work with the government to see how we move the sector forward,” the CPPE boss said.

While acknowledging that there is a need for a major reform in the power sector, Yusuf nonetheless admitted that in this aspect, the President has done very well to clear the legacy debt

“The clearing of the legacy debt will also improve the stability of electricity because what we have had in the last few months is that because of the debt, gas suppliers were not paid. And because gas suppliers were not paid, they were not able to supply gas to the generating companies.

“And because the generating companies don’t have enough power, they are not able to generate. And at a time like this, I think we are depending almost 80 or 90 per cent on the thermal power plants which are using gas. So this will improve liquidity in the value chain, particularly with the gas suppliers and the generating companies.

“And once the liquidity improves, of course we have more power generated and transmitted. So it’s going to have a major significant impact in terms of the provisional improvements in the electricity supply,” Dr. Yusuf concluded.

 

 

Continue Reading

Power

World bank, partners launch council to drive power access and jobs in Africa

Published

on

Akintunde Olamide

The World Bank Group, alongside the African Development Bank and The Rockefeller Foundation, has unveiled a new Mission 300 Private Sector Council aimed at unlocking billions of dollars in private investment to expand electricity access and create jobs across Africa.

The initiative targets connecting 300 million Africans to electricity by 2030, while accelerating economic growth and employment opportunities across the continent.

Fourteen business leaders drawn from various industries will guide strategies to attract capital, strengthen deal making capacity, and scale up innovative financing particularly in local currencies. The council will be co-chaired by Makhtar Diop of the International Finance Corporation and Ray Chambers.

Speaking on the initiative, Diop emphasized that achieving Mission 300 requires large scale private sector participation and practical strategies shaped by experienced industry players. He noted that the council brings together influential leaders capable of turning ambitious plans into tangible results.

Mission 300 is a joint effort by the World Bank and African Development Bank, supported by partners including the Global Energy Alliance for People and Planet and Sustainable Energy for All. The programme seeks to significantly expand electricity access while boosting job creation.

Currently, nearly 600 million people in Africa lack electricity. Addressing this gap will require unprecedented levels of investment, speed, and collaboration particularly from the private sector. To support this, the IFC and the Multilateral Investment Guarantee Agency have pledged $5 billion toward private sector investments under Mission 300 by 2030.

Since its launch in 2024, Mission 300 has already connected 44 million people to electricity. Additionally, 30 countries have signed energy compacts aimed at expanding infrastructure, promoting renewable energy, strengthening regional power integration, and encouraging private investment.

Dr. Kevin Kariuki described the council as a major step toward accelerating investment flows, noting that about half of the funding for energy compacts is expected to come from private sector players. He added that involving business leaders would help bridge the gap between policy reforms, financing, and viable projects, ultimately driving faster delivery and job creation.

Half of the targeted electricity connections under Mission 300 are expected to come from off-grid solutions, making private investment essential in expanding decentralized energy systems. Andrew Herscowitz said the Mission 300 Accelerator will work closely with partners and the council to fast-track commercial investments and improve lives across Africa.

The Private Sector Council includes representatives from companies such as Airtel Africa Plc, Elsewedy Electric, EQT Corporation, Standard Bank, and TotalEnergies, among others.